Friday, August 8, 2008

Lester rented a crane and a man lift to put up the remaining 2 rpsl's and the ridge pole. He also used the crane to put in the top girder since they were coming out anyways.  We measured and remeasured the ridge pole support logs and the ridge pole but the center pole was a little short so Lester had to saw some off the top of the back rpsl to make everything fit in place. 
Now we will have to wait a month to get our rough sawn rafters to start on the roof. We may have to sub-contract that out because we are getting into our busy season at the shop and Lester cannot take off as much. We would like to have the cabin under roof before the snow starts falling.   